Who Pulls the Permit, and Why It Matters
Reading time: about 5 minutes
TLDR
- A permit is pulled either by a licensed contractor or by the homeowner, and whoever holds it carries the liability.
- The job card is the record that every stage was inspected and passed.
- Unpermitted work surfaces at sale, at insurance claim, and at your next permit application.
- Incomplete applications and uncoordinated drawings are common causes of delay.
Almost everything major done to a house needs a permit. Structural work, additions, ADUs, a gas line run out to an outdoor kitchen, a window opening that changes size.
Whose name goes on that permit decides who is liable for the work.
What a permit application rests on
A permit application is built on a coordinated set of drawings. The architectural drawings describe what is being built. The structural drawings describe what holds it up. Both are reviewed, and both have to be consistent with each other and with what the code requires before anything is stamped.
Depending on jurisdiction and scope, a project may also go through planning review, which looks at questions the building code does not: how the work sits in its context, what is visible from the street, and what the neighborhood requires. On a protected property such as a San Francisco Victorian, planning review is where it is established that the work is in keeping with the existing architecture.
Timelines vary considerably between jurisdictions.
Two ways a permit gets pulled
A permit for residential work is pulled either by a licensed contractor or by the property owner, under what is called an owner builder permit.
When a licensed contractor pulls the permit, the contractor’s name and license number are on the job card. The contractor is the party responsible for the work, the party the inspector deals with, and the party who has to stand over what was built.
When a homeowner pulls an owner builder permit, all of that sits with the homeowner. You are the permit holder, the liability for the work is yours, and you are the party the building department looks to.
What the job card actually is
The job card is the document posted on site through construction. Inspectors sign it at each stage: foundation, framing, rough electrical and plumbing, insulation, and so on through to final.
A signed off job card is the record that the work was inspected and passed at every stage. That record is what a future buyer, a future lender and a future insurer will look for, which is why the final sign off matters as much as the permit itself.
Why owner builder permits appeal
People pull their own permits for understandable reasons. Doing so can look like a saving, and for genuinely small self performed work it sometimes is.
Some clients come to us having already pulled one, and we are happy to come in and do the work. What is worth understanding before you choose that route is what changes: the permit holder is you, the liability sits with you rather than with your contractor, and the responsibility for making sure every stage is inspected and signed off is yours.
Inspections through the build
A permit is a sequence of inspections running alongside construction, and each one has to pass before the work it covers can be covered up.
Foundation inspection happens before concrete is poured, with the forms and the reinforcing steel in place. Framing inspection happens once the structure is up and before insulation goes in. Rough electrical, plumbing and mechanical are inspected while the walls are still open. Insulation is inspected before drywall. Then drywall, and eventually final.
Sequencing that properly is a scheduling exercise, because an inspection that has not happened blocks everything behind it.
When an inspection does not pass
Inspections sometimes turn up corrections, and that is a normal part of the process rather than a failure.
An inspector may want additional blocking, a different fastener, or clarification on how something in the drawings has been executed. The correction is made, the inspector returns, and the work proceeds.
What matters is who is managing that exchange. When the contractor holds the permit, the inspector deals with the contractor, and the correction is handled as part of the job. When the homeowner holds it, that conversation is theirs.
Unpermitted work catches up
Unpermitted work surfaces at three predictable moments.
The first is sale. Disclosure obligations mean unpermitted work has to be declared, and a buyer will discount for it or ask for it to be resolved before closing.
The second is insurance. A claim arising from work that was never permitted or inspected is a considerably more difficult conversation than one arising from work that was.
The third is any subsequent project. When you next apply for a permit, the department sees the property record, and unpermitted work discovered at that point has to be dealt with before the new project can proceed.
Retroactive permitting is possible, though slower, more expensive and occasionally impossible, because proving what is behind a finished wall means opening it up.
Repairs and in-kind work
Not everything requires a full permit set. When work is a genuine in-kind repair or replacement, replacing something that already exists with the same thing in the same place, the permitting route is usually simpler and faster.
When a repair turns into a change, whether that is a different size opening, a different structural arrangement or additional square footage, the work does not qualify and the full route applies.
What actually causes delay
One common cause is an incomplete application, which does not start any clock and simply sits until the missing item arrives. Another is a conflict between the architectural and structural drawings that a reviewer catches, which sends the drawings back for coordination that should have happened before submission. A third is a scope that turns out to need planning review when nobody expected it, which adds a whole process rather than a delay within one.
How we handle it
We pull the permit in our own name. Our name is on the job card, we deal with the inspectors, and we take the project through to a signed off card at the end.
We also handle the coordination that gets an application accepted in the first place, which is where most delay originates. An incomplete application does not start any clock, and completeness is the part we control.