Why San Francisco Seismic Requirements Went Up in 2026, and What It Means for Your Remodel

Jonathan "Johnny" Croke • August 17, 2026

Reading time: about 6 minutes

TLDR

  • In 2026 the seismic load requirement in San Francisco increased by 10 percent.
  • Your permit is reviewed against the code in force when you submit, not when you started designing.
  • A 10 percent change in the load does not translate to 10 percent more work.
  • Your soil and slope affect the load as much as the code does, which is why pricing cannot come from a walkthrough.

In 2026 the seismic load requirement in San Francisco increased by 10 percent. If you are planning a remodel, an addition or any structural work in the city, that change affects what your engineer specifies and what the work costs.

The timing of a permit submission can decide which version of the code your project is measured against.

What a seismic load requirement is

When an engineer designs the structure of a building, they are designing it to resist forces. Gravity is the obvious one, pulling everything down. The other is lateral force, which pushes sideways, and in this region the main source of lateral force is an earthquake.

The seismic load is the sideways force the structure is required to be able to resist without failing. The number comes out of ground motion data, fault mapping, soil conditions and the accumulated record of what actually happens to buildings during earthquakes.

When the required load goes up by 10 percent, every element in the lateral system has to be able to handle 10 percent more. In practice that means more shear panels or larger ones, more hold downs, heavier connections, and in some cases a moment frame where a shear wall would previously have been sufficient.

Why building codes change

Codes are revised on a regular cycle rather than in response to any single event, and each revision folds in new research and new data. Ground motion modeling improves. Fault mapping gets more precise. Engineers study what failed and what held in earthquakes here and elsewhere, and the requirements move accordingly.

Your permit is reviewed against the code in force when you submit

A building permit is assessed against the code in effect at the time the application is submitted, not the code that applied when you started thinking about the project, and not the code that applies when construction begins.

For most projects the timing is simply a fact to be aware of. For a project that has been in design for a while, or one where drawings have been sitting waiting for a decision, it can mean a set of structural drawings needs revisiting before submission.

What changes on your project

For a straightforward interior remodel with no structural work, nothing changes. The seismic requirement applies to the structure, so if you are not touching the structure it does not arise.

For anything structural, the effect shows up on the engineered drawings. You will see more plywood shear panels and more nailing, more and heavier hold downs, larger framing members or engineered lumber where standard sections would previously have done, and steel specified in situations that used to be resolved in wood.

As a proportion of a whole project the additional cost is usually modest, because most of the expense in structural work is access and labor rather than the material itself. Adding more nails to a shear panel that is already being installed costs very little. Adding a shear panel to a wall that has to be opened up specially costs a great deal more.

Green residential building with exterior stairs, bay windows, and blue recycling bins in a driveway.

What 10 percent looks like on a wall

Take a shear wall in a garage, sheathed in structural plywood and nailed to a schedule the engineer specifies. The nailing schedule is what makes a shear panel work: how far apart the nails sit along the edges of each sheet, and how far in from the edge they land.

A higher required load means a tighter schedule, closer nail spacing, and often a thicker sheet. A tighter schedule can also mean the panel needs a hold down at each end where it previously did not, and hold downs transfer uplift into the foundation, which means the foundation under that wall has to be able to take it.

That chain of requirements is why a 10 percent change in the headline number does not always translate to a 10 percent change in the work, and why the engineered drawings are the only reliable guide to what your project actually needs.

Your ground matters as much as the code

Two houses on the same street can carry different seismic requirements, because the load an engineer designs for depends on what the building is standing on as well as what the code asks for.

Soil type is the main variable. Dense rock transmits ground motion differently from soft or filled ground, and soft soil can amplify shaking considerably. Slope matters too, since a hillside property has lateral forces acting on it that a flat lot does not, and the foundation has to resist both.

Large parts of the Bay Area sit on ground that has been modified over the last century and a half, whether that is fill, former marsh, or a hillside that has been cut and benched to make a building pad.

Ground conditions are one of several reasons a price for structural work cannot come from a walkthrough.

What it does not mean

A code change does not make your existing house non compliant. Buildings are assessed against the code in force when they were permitted, and a house built to the 1955 code remains a legal building.

What a code change does is set the standard for new work. When you build something new, or when you alter enough of the existing structure that the permit requires it, the new work meets the current standard.

What to do if you are mid-design

If your project has been drawn but not yet submitted, it is worth a conversation with your engineer before the application goes in. A set of drawings prepared against the previous requirement will be reviewed against the current one, and finding that out at plan check costs more time than checking it now.

If you are not doing a remodel

Plenty of people read about a code change and wonder whether they should do something about their own house regardless.

A voluntary upgrade is always available. You are not obliged to wait for a remodel or an addition, and the work is the same work: foundation bolting, cripple wall bracing, shear panels and hold downs, designed by an engineer and installed to their drawings.

What changes is the cost, because a voluntary retrofit pays for access that a remodel would have provided anyway. On a house with an accessible crawl space or an unfinished garage, that difference is small and a standalone retrofit makes good sense. On a house where the relevant walls are finished, it is worth considering whether the work is better done alongside something else you already want.

Strengthening a building that already exists keeps it standing and in use, which is a better outcome for the material in it than any replacement.

 I know Johnny from Caliber Construction and can confidently recommend him. His knowledge of structural work is solid, and he stands out in organizing trades and preconstruction planning. He knows how to navigate the ins and outs of both new construction and remodeling; he thinks ahead and keeps projects moving in the right direction. If you’re in the Bay Area and need a GC who knows what he’s doing, Johnny has the skills and knowledge to get the job done right.